Sikafloor-82 EpoCem, Epoxy-Cement Slab, 4-7mm
SIKA
Sika is a global leader in specialty chemicals for the construction and industrial sectors. The company develops and supplies innovative products and systems for bonding, sealing, damping, reinforcing, and protecting structures. With a strong focus on sustainability and performance, Sika serves a wide range of applications including concrete production, waterproofing, roofing, flooring, and structural strengthening.
Read moreEpoxy-cement hybrid for self-smoothing floor screeds (3 to 7 mm (0.276 in)) Sikafloor®-82 EpoCem® is a three part, epoxy modified cementitious, fine textured mortar for self-smoothing floor screeds in layers of 3 to 7 mm (0.276 in). It allows the application of epoxy, polyurethane and PMMA resin floors over high moisture content substrates or green concrete. | ||||||||||||||||||||||||||||||||||||||||||||||||
UsageThe Product is used as a:
Please note:
Advantages
Packaging
ColourFinal floor appearance: Smooth, matt finish
Note: When the Product is exposed to direct sunlight, there may be some discolouration and colour variation. This has no influence on the function and performance of the Product. | ||||||||||||||||||||||||||||||||||||||||||||||||
Typical Product Data
| ||||||||||||||||||||||||||||||||||||||||||||||||
ApplicationMixing ratio At temperatures between +12 °C (+54 °F) to +25 °C (+77 °F):
At temperatures between +8 °C (+46 °F) to +12 °C (+54 °F) and +25 °C (+77 °F) to +30 °C (+86 °F): The amount of part C can be reduced to 24 kg (52.9 lb) in order to improve workability. Never reduce part C by more than this amount.
Note: For this application, to achieve a good bond of the mortar to the substrate, SikaTop® Armatec®-110 EpoCem® must be used as a primer. Apply the mortar wet on wet to the primer. Layer thickness
Note: If the Product is used as a Temporary Moisture Barrier (TMB), a minimum of 3 mm (0.118 in) must be applied. Product temperature
Ambient air temperature
Relative air humidity
Substrate temperature
Substrate moisture content Can be applied on green or damp concrete, without any standing water. Although the product can be applied onto green concrete surfaces (> 24 hours), it is advised to allow at least 3 days for early shrinkage of concrete to occur in order to prevent concrete shrinkage cracks from appearing on the screed surface. Pot life
Curing time Once Sikafloor®-82 EpoCem® is tack free it is possible to apply vapour permeable seal coats. For the application of vapour tight coatings on Sikafloor®-82 EpoCem®, allow the surface moisture to fall below 4 %, not earlier than:
Consumption
Note: Consumption data is theoretical and does not allow for any additional material due to surface porosity, surface profile, variations in level, wastage or any other variations. Apply product to a test area to calculate the exact consumption for the specific substrate conditions and proposed application equipment. EQUIPMENT MIXING EQUIPMENT
APPLICATION EQUIPMENT
SUBSTRATE QUALITY IMPORTANT Incorrect treatment of cracks The incorrect assessment and treatment of cracks may lead to a reduced service life and reflective cracking. TREATMENT OF JOINTS AND CRACKS Construction joints and existing static surface cracks in substrate require pre-treating before full layer application. Use Sikadur® or Sikafloor® resins. SUBSTRATE CONDITION Cementitious substrates (concrete / screed) must be structurally sound and of sufficient compressive strength (minimum 25 N/mm 2 (3626 psi) ) with a minimum tensile strength of 1.5 N/mm 2 (218 psi) . SUBSTRATE PREPARATION MECHANICAL SUBSTRATE PREPARATION IMPORTANT Exposing blow holes and voids When mechanically preparing the surface, make sure to fully expose blow holes and voids.
Contact Sika® Technical Services for additional information on products for levelling and repairing defects. SUBSTRATE PREPARATION OF NON-CEMENTITIOUS SUBSTRATES For information on substrate preparation of non-cementitious substrates, contact Sika technical services. MIXING IMPORTANT Addition of water Do not add water to the mix or for finishing as this will affect the performance, surface finish and cause discolouration. IMPORTANT Unsuitable mixing equipment Do not use free fall mixers. IMPORTANT Avoid over-mixing to minimise air entrainment.
APPLICATION IMPORTANT Strictly follow installation procedures Strictly follow installation procedures as defined in Method Statements, application manuals and working instructions which must always be adjusted to the actual site conditions. IMPORTANT Protect from moisture After application, protect the Product from damp, condensation and direct water contact for at least 24 hours. IMPORTANT Ventilation in confined spaces Always ensure good ventilation when applying the Product in a confined space. IMPORTANT Pin holes If the Product is applied on porous substrates during rising temperatures, pin holes may form from rising air.
IMPORTANT Do not use curing compounds Applications under extreme conditions (high temperature and low humidity) which can cause fast drying of the product must be avoided as the product does not allow the use of curing compounds. IMPORTANT Protect fresh Product from direct sunlight and draughts To reduce the risk of cracking, protect freshly applied product from high ambient temperatures, direct sunlight and draughts.
Overcoating with PMMA Note: When overlaying with PMMA screeds, the Product surface must be fully broadcast with clean and dry quartz sand. Moisture barrier Note: The TMB effect is limited in time without additional preparation. Always verify the surface moisture content if more than 5 days have passed since application. CLEANING OF TOOLS Clean all tools and application equipment with water immediately after use. Hardened material can only be removed mechanically. |